Commercial · 2024
Office floors, Kirchberg
Bleu Ardenne#1E4E6B
- Municipality
- Luxembourg-Kirchberg
- Area
- 1450 m²
- Duration
- 31 working days
- Year
- 2024
The context
One thousand four hundred and fifty square metres over three floors, to be made good between two tenants. Window: five weeks, with no possibility of overrun.
The constraint
The programme left no slack and the building remained occupied on the lower floors. We worked two staggered teams from 6 a.m. to 10 p.m., handing over a complete floor each week. The deep blue in the meeting zones took three coats: a dark colour on a pale partition forgives nothing.
Before / after
BeforeAfterGris bureau#8B9298Bleu Ardenne#1E4E6B
Let's talk about your project.
A site visit, a detailed quote within 48 hours, no obligation.
Request a quote